top of page

List of Projects under Sarawak Energy Berhad (SEB)

No.
Project
Main Contractor
Job Scope
Job Status
1
Stakan - 132/33kV Substation Project
SEE Energy Sdn. Bhd.
Cabling & termination works
Completed, Dec 2015
2
Tudan - 275/33kV Substation Project
Alstom Services Sdn. Bhd.
Supervise the Cu. Tape Exothermic Joint Works
Completed, Apr 2018
3
Similajau - 275kV Substation Capacitor Bank Project
Alstom Services Sdn. Bhd.
Overall Erection & Cabling Works
Completed, Dec 2015
4
Deshon - 132/33kV Substation Project
SEE Energy Sdn. Bhd.
Overall Erection & Cabling Works
Completed, Jul 2017
5
Kemena - 275kV Substation
P.E.S.B. Engineering Sdn. Bhd.
Replacement of Shunt Reactor
Completed, Sep 2018
6
Mendu - 132kV Substation Project
P.E.S.B. Engineering Sdn. Bhd.
Power Cable Laying & Termination Works
Completed, Nov 2018
7
Samalaju B - 275kV GIS Substation Project
L&T Ptl. Ltd.
Earthing System & Cabling Works
Completed, Jul 2018
8
Marudi Junction - 275kV Substation Project
L&T Ptl. Ltd.
Overall Erection & Cabling Works
Completd, Nov 2018
9
Daro - 132kV AIS Substation Project
M.A. Prestige Sdn. Bhd.
Overall Erection & Cabling Works
Completd, Mar 2018
10
Kemantan - 132kV Substation Extension Kapit - 132/33kV Substation Project
ABB Malaysia Sdn. Bhd.
Overall Erection & Cabling Works
Completed, Apr 2018
11
Bintulu 2 - 275kV / 33kV GIS Substation Project
PESTECH Sdn. Bhd.
Copper Tape, Cable Termination Work & Manpower Supply
Completed, Mar 2019
12
Lanchau – Upgrading 1 unit transformer 275/33kV
PESTECH Sdn. Bhd.
Overall Erection & Cabling Works
Completed, May 2021
13
Kanowit – 33/132kV GIS New Substation
TCF EHV Enterprise
132kV Cabling Work
Completed, Jul 2021
14
Lundu – 33kV Substation CENTEXS
Unique Deco Sdn. Bhd.
Overall Erection & Cabling Works
Completed, Jan 2021
15
Lawas - 275/33kV Substation Project
Larsen & Toubro Limited, Construction
Overall Erection & Cabling Works
Completed, Jun 2022
16
Bunut – (500)/275/(132)/33kV Substation Project
Shanghai Electric Power T&D (M) Sdn. Bhd.
Overall Erection & Cabling Works
Completed, Jun 2022
17
Sg. Merah – 132/33kV Substation & 132kV Extension Project
P.E.S.B. Engineering Sdn. Bhd.
Overall Erection & Cabling Works
Completed, Aug 2022
18
Deshon Substation (Sibu)
MYS Engineering Sdn. Bhd.
3 sets of 132kV Circuit breaker replacement Works
Completed, Oct 2021
19
Tondong - 275kV Substation
ABB Power Grids Malaysia Sdn. Bhd.
Overall Erection & Cabling Works
Completed, Jan 2023
20
Limbang Power Station
WZS Powergen Sdn. Bhd.
Supply, Delivery, Installation and Commissioning of 8 * 1250kVa Diesel Engine Generating Sets and 8 * 1500kVa 0.415/11 kV Step-Up Transformer
Completed, Apr 2023
21
Oya Substation
SEB
Emergency Replacement Works For 132kv Oya Auto Transformer No. 2 Bay G3TO Circuit Breaker
Completed, July 2023
22
Sejingkat Power Corporation
CEEC JSPI (Malaysia) Sdn. Bhd.
Installation Works of Sejingkat Power Corporation 60MWac Battery Energy Storage System Project
Completed, Feb 2025
23
Bintulu B – Shell 132kV Shell Substation
P.E.S.B. Engineering Sdn. Bhd.
Overall Erection & Cabling Works
On Going
24
Bintulu Power Plant – 275kV Substation
Shanghai Electric Power T&D (M) Sdn. Bhd.
Overall Erection & Cabling Works
On Going
25
50MWac Batang Ai Floating Solar Project
CEEC JSPI (Malaysia) Sdn. Bhd.
275KV Substation and Extension Bay Installation Works
Completed, Dec 2024
26
Malaysia LNG, Bintulu
Hitachi Energy Malaysia Sdn. Bhd.
Supply & Delivery Control Relay Panel & 33KV GIS Switchgear
On Going
27
Pending 33/11kV Substation, Kuching
JW Eco Builders Sdn. Bhd.
Civil Overall Contract Works
On Going
bottom of page